enCore Energy completes first-phase construction at Upper Spring Creek ISR uranium IX plant
enCore Energy Corp.
enCore Energy Corp. EU | 0.00 |
- enCore Energy completed first-phase construction of the Upper Spring Creek ISR uranium project’s satellite ion-exchange plant in South Texas.
- Built capacity reaches 1,600 gallons per minute, or 50% of planned throughput; full 3,200 gallons per minute targeted by end-July.
- First production wellfield nears completion; uranium extraction to start once final permits are received.
- Project designed to supply uranium-loaded resin to the fully licensed Rosita central processing plant; operations targeted for late 2026.
Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. enCore Energy Corp. published the original content used to generate this news brief via PR Newswire (Ref. ID: 202606040710PR_NEWS_USPR_____VA76020) on June 04, 2026, and is solely responsible for the information contained therein.