Vista Gold publishes investor presentation outlining Mt Todd gold project development plan and economics
Vista Gold Corp.
Vista Gold Corp. VGZ | 0.00 |
- Vista Gold highlighted Mt Todd as a 15,000 tpd development plan with initial capex of USD 425 million.
- Feasibility metrics: 30-year mine life; average production 153,000 oz/year in years 1-15; AISC USD 1,449/oz in years 1-15.
- After-tax NPV(5%) USD 1.1 billion at USD 2,500 gold; USD 2.2 billion at USD 3,300; USD 3.8 billion at USD 4,500.
- After-tax IRR 27.8% at USD 2,500 gold; 44.7% at USD 3,300; 66.3% at USD 4,500.
- Cash USD 52.7 million as of March 31, 2026; no debt; work programs target detailed engineering and design in 2027; first gold targeted late 2029.
Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Vista Gold Corporation published the original content used to generate this news brief on June 26, 2026, and is solely responsible for the information contained therein.