UPDATE 1-Orsted plans US Sunrise Wind for H2 2027, says Revolution back on track

Dow Jones Industrial Average -1.18%
S&P 500 index -0.92%
NASDAQ -0.84%

Dow Jones Industrial Average

DJI

46590.24

-1.18%

S&P 500 index

SPX

6672.41

-0.92%

NASDAQ

IXIC

22708.07

-0.84%

Adds detail on Revolution Wind project in paragraphs 2-3

- Danish offshore wind developer Orsted ORSTED.CO maintains a plan to complete its offshore Sunrise Wind project in the United States in the second half of 2027, the company's CEO Rasmus Errboe told reporters on Tuesday.

Orsted has meanwhile fully resumed work on the 80% complete U.S. Revolution Wind project, after a federal judge last month lifted a work-stop order the company had received from the administration of President Donald Trump in August.

Orsted still expects Revolution Wind to be operational by the second quarter of 2026, Errboe said.


(Reporting by Jacob Gronholt-Pedersen, writing by Louise Breusch Rasmussen, editing by Terje Solsvik)