BRIEF-B2gold Reports Update On Fire-Related Incident To The Crushing Circuit At The Goose Mine

John Hancock Financial Opportunities Fund

John Hancock Financial Opportunities Fund

BTO

0.00

- B2Gold Corp BTO.TO:

  • B2GOLD REPORTS UPDATE ON FIRE-RELATED INCIDENT TO THE CRUSHING CIRCUIT AT THE GOOSE MINE

  • B2GOLD CORP - NO INJURIES REPORTED IN GOOSE MINE FIRE

  • B2GOLD CORP - FIRE DAMAGE WAS LOCALIZED TO CRUSHING CIRCUIT AREA

  • B2GOLD CORP - ADDITIONAL TEMPORARY CRUSHING CAPACITY TO BE TRANSPORTED TO GOOSE MINE IN Q2 2026

  • B2GOLD CORP - THERE WAS NO DAMAGE OR IMPACT TO MILL OR POWER FACILITY

  • B2GOLD CORP - PRELIMINARY ESTIMATE FOR CRUSHING CIRCUIT FIRE REPAIRS IS C$10 MILLION

  • B2GOLD CORP - DUE TO IMPACT TO CRUSHING CIRCUIT RELATED TO FIRE, COMPANY NOW FORECASTS GOLD PRODUCTION IN Q2 OF 2026 OF 18,000 TO 20,000 OUNCES

Source text: ID:nGNX99zHWF

Further company coverage: BTO.TO