BRIEF-Pembina Pipeline Announces Positive Final Investment Decision On Greenlight Electricity Centre
PPL Corporation PPL | 0.00 |
July 2 (Reuters) - Pembina Pipeline Corp PPL.TO:
PEMBINA PIPELINE ANNOUNCES POSITIVE FINAL INVESTMENT DECISION ON THE GREENLIGHT ELECTRICITY CENTRE
PEMBINA PIPELINE CORP - GREENLIGHT ELECTRICITY CENTRE TO BE 932 MW GAS-FIRED POWER FACILITY IN ALBERTA
PEMBINA PIPELINE CORP - GREENLIGHT PROJECT COST EXPECTED AT $4.6 BILLION, $2.3 BILLION NET TO PEMBINA
PEMBINA PIPELINE CORP - PROJECT EXPECTED TO GENERATE ANNUAL RUN-RATE ADJUSTED EBITDA OF $310 MILLION NET TO PEMBINA
PEMBINA PIPELINE CORP - GREENLIGHT ELECTRICITY CENTRE ANTICIPATED IN-SERVICE DATE SECOND HALF OF 2030
PEMBINA PIPELINE CORP - GREENLIGHT TO FINANCE 60% OF PROJECT COST WITH DEBT, 40% WITH EQUITY
PEMBINA PIPELINE CORP: PEMBINA AND MSIP WILL FUND 50% OF GREENLIGHT'S CAPITAL
PEMBINA PIPELINE CORP: ALL FINANCIAL FIGURES ARE IN CANADIAN DOLLARS
Source text: ID:nBwcChSFa
Further company coverage: PPL.TO