BUZZ-US energy shares rise after FID, EPC deal for Big Sky Carbon Hub project
U.S. Energy Corp. USEG | 0.00 |
** Shares of U.S. Energy Corp USEG.O rise 3% to $1.04 premarket
** Co says it has reached a Final Investment Decision (FID) for the construction of its processing facility at the Big Sky Carbon Hub in Montana
** Co adds that it executed an Engineering, Procurement and Construction (EPC) agreement with CANUSA EPC under a fixed-scope EPC contract structure
** The EPC deal established a defined budget and contingency and was completed alongside the FID as a final pre-construction step
** Co says pipeline installation will start in spring 2026, commissioning is expected in Q3 2026 and initial helium sales and carbon management operations in Q1 2027
** Up to last close, USEG up 9.4% YTD