Dakota Gold publishes investor presentation on Richmond Hill gold project development in Homestake District
Dakota Gold Corp
Dakota Gold Corp DC | 0.00 |
- Dakota Gold outlined a plan to advance the Richmond Hill heap-leach project, targeting first production as soon as 2029.
- Richmond Hill S-K 1300 heap-leachable resource: 3.65 million oz M&I gold, 2.61 million oz inferred gold; 38.1 million oz M&I silver.
- Initial assessment economics at US $2,350/oz gold: after-tax NPV5% US $1.6 billion; IRR 55%; initial capex US $384 million.
- Mine plan: 17-year life; 153,000 oz average annual gold; LOM AISC US $1,047/oz; payable gold 2.6 million oz.
- Cash balance US $107 million as of Mar. 31, 2026; pre-feasibility study targeted H2 2026; feasibility study targeted H1 2027.
Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Dakota Gold Corporation published the original content used to generate this news brief on June 02, 2026, and is solely responsible for the information contained therein.