ENKA, GE Vernova start commercial operations at 852 MW Kırklareli gas plant in Türkiye
GE Vernova
GE Vernova GEV | 0.00 |
- GE Vernova marked start of commercial operations at ENKA’s 852 MW Kırklareli natural gas combined-cycle power plant in Türkiye, first HA-powered plant in the country.
- Project uses a 9HA.02 H-class gas turbine, first H-class unit installed in Türkiye, positioning the facility as one of the country’s most efficient combined-cycle plants at above 63% net efficiency.
- Multi-year agreement calls for GE Vernova to provide long-term maintenance services aimed at improving reliability, availability, and asset visibility.
- ENKA executed engineering, procurement, construction, and commissioning over 36 months, totaling about 8 million person-hours.
- GE Vernova said its installed gas power capacity in Türkiye has reached about 13.5 GW, part of an overall installed base of roughly 33.5 GW across power and grid technologies.
Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. GE Vernova Inc. published the original content used to generate this news brief on May 12, 2026, and is solely responsible for the information contained therein.