Fermi selects Primoris to engineer, build balance of plant for first six SGT-800 turbines in Texas power project

Primoris Services Corporation
Fermi Inc.

Primoris Services Corporation

PRIM

0.00

Fermi Inc.

FRMI

0.00

  • Fermi awarded Primoris Energy Services an engineering and construction contract for balance-of-plant work tied to six Siemens SGT-800 gas turbines.
  • Scope covers engineering, procurement, construction for the simple-cycle phase of a Siemens 6x1 combined-cycle facility serving Project Matador in Amarillo, Texas.
  • Primoris previously mobilized on site, completed excavation for six turbine power islands, received balance-of-plant materials for underground utility installation.
  • Work supports Phase One power buildout, targeting faster delivery for power supply to the adjacent hyperscale computing and data center campus.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Fermi Inc. published the original content used to generate this news brief via PR Newswire (Ref. ID: 202606300830PR_NEWS_USPR_____NY95266) on June 30, 2026, and is solely responsible for the information contained therein.