Gunnison Copper releases investor presentation outlining Arizona Gunnison project development plan and PEA economics
- Gunnison Copper outlined a 2026 PEA for its Arizona Gunnison Project, targeting a 21-year open-pit heap-leach SX/EW copper cathode operation.
- After-tax NPV at 8% of USD 1.96 billion, after-tax IRR 22.5% at USD 4.6/lb copper; initial capex with acid plant USD 1.56 billion.
- Average annual copper cathode output about 174 million lbs; total recovered copper 3.2 billion lbs; AISC USD 2.05/lb; payback 3.9 years.
- First copper production projected for 2030 in an accelerated case, or 2032 in a base case.
- Permitting strategy centers on amendments to existing Arizona permits; interstate relocation process for a 2.8-mile I-10 segment slated to start in Q2 2026.
Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Gunnison Copper Corp. published the original content used to generate this news brief on July 14, 2026, and is solely responsible for the information contained therein.