Hawaiian Electric orders GE Vernova aeroderivative turbines for Waiau plant modernization
GE Vernova Inc.
Hawaiian Electric Industries, Inc.
GE Vernova Inc. GEV | 0.00 | |
Hawaiian Electric Industries, Inc. HE | 0.00 |
- Hawaiian Electric placed orders for GE Vernova aeroderivative combustion turbines, securing equipment slots for the Waiau Power Plant repowering.
- Orders also cover replacement transformers, with down payments made as global demand tightens supply for similar units.
- Project targets first two units in commercial operation in 2029, with additional units slated for 2031 and 2033.
- Repowering will replace six steam generators, adding 252 MW of firm capacity with lower emissions and improved efficiency.
Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. HEI - Hawaiian Electric Industries Inc. published the original content used to generate this news brief on June 03, 2026, and is solely responsible for the information contained therein.
