Hyperscale Data plans Montana data center expansion after utility clears up to 125 MW power increase
Hyperscale Data, Inc.
Hyperscale Data, Inc. GPUS | 0.00 |
- Hyperscale Data moved to advance development at a Montana site after a utility “will serve” determination for up to 125 MW of additional power.
- The facility currently runs about 10 MW for Bitcoin mining; the added capacity remains conditional on studies, upgrades, approvals, funding, milestones.
- No timeline was provided for required improvements; one needed transmission line is being pursued with a 2031 completion timeframe.
- A second Montana location about 15 miles away runs about 10 MW; a load study is being considered to assess incremental capacity.
Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Hyperscale Data Inc. published the original content used to generate this news brief via PR Newswire (Ref. ID: 202606241437PR_NEWS_USPR_____SF91626) on June 24, 2026, and is solely responsible for the information contained therein.