Minera Alamos fast-tracks Copperstone gold project after PFS pegs after-tax NPV at $374 million

  • Minera Alamos released a pre-feasibility study for its Copperstone underground gold project in Arizona, targeting first production in mid-2027.
  • After-tax NPV5% USD 374 million at USD 3,500/oz gold; after-tax IRR 108%; payback 1.2 years; undiscounted net cashflow USD 512 million.
  • Initial capex USD 58.3 million; sustaining capex USD 76.9 million; financing planned from cash, a revolving credit facility, Pan mine cash flow.
  • 6.3-year mine plan targets 291,000 oz produced; average annual output 46,000 oz; total cash costs USD 1,070/oz; AISC USD 1,314/oz.
  • Maiden proven and probable reserves of 303,000 oz at 4.87 g/t; measured and indicated resources 630,000 oz at 4.83 g/t.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Minera Alamos Inc. published the original content used to generate this news brief on May 27, 2026, and is solely responsible for the information contained therein.