- Oracle urged New Mexico regulators to clear an updated air permit for its Project Jupiter AI data center campus in Doña Ana County.
- Energy plan shifts to Bloom Energy fuel cells, replacing proposed gas turbines and diesel generators; expected to cut CO2 emissions 21%.
- Projected reductions versus the prior plan include nitrogen oxides 92%, carbon monoxide 67%, particulate matter 83%.
- Cooling design uses closed-loop, non-evaporative direct-to-chip systems; operations would avoid using the local public drinking-water supply.
- Project outlines $360 million in direct payments to the county, $50 million for local water-system upgrades, 4,000 construction jobs, 1,500 ongoing jobs.
Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Oracle Corporation published the original content used to generate this news brief on July 02, 2026, and is solely responsible for the information contained therein.