Tallgrass, Mitsubishi allocate first two M501JAC turbines for Cheyenne Power Hub Phase 1

  • Tallgrass allocated first two Mitsubishi Power M501JAC gas turbines to Phase 1 of Cheyenne Power Hub in southeast Wyoming, targeting about 1,150 MW of site-ready generation fueled by natural gas from Rockies Express Pipeline.
  • Project investment expected to exceed $7 billion, supporting dedicated on-site power for a large-scale data center at Switchgrass Industrial Park.
  • Design includes a grid interconnection to enable future renewable integration, with proximity to Tallgrass’ Trailblazer carbon capture and sequestration project positioned as a pathway for further decarbonization.
  • Delivery and installation of components for first turbine unit expected to begin as early as July.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Tallgrass Energy LP published the original content used to generate this news brief on May 15, 2026, and is solely responsible for the information contained therein.