Wärtsilä wins 790 MW Texas off-grid data center power plant order

  • Wärtsilä booked order intake in Q2 2026 to supply 790 MW off-grid power plant for new Texas data center.
  • Project uses 42 Wärtsilä 50SG natural gas engines.
  • Equipment delivery scheduled for 2028.
  • Plant expected to reach full operations in late 2029.
  • Order is Wärtsilä’s first data center-related deal in Texas, bringing total U.S. data center capacity sold to more than 2.4 GW.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Wärtsilä Oyj published the original content used to generate this news brief on April 23, 2026, and is solely responsible for the information contained therein.